MainMenu

Home Java Overview Maven Tutorials

ISTQB Practice set 14

ISTQB Question Paper - 14
1. Designing the test environment set-up and identifying any required infrastructure and tools are a part of which phase
a) Test Implementation and execution
b) Test Analysis and Design
c) Evaluating the Exit Criteria and reporting
d) Test Closure Activities

2. Test Implementation and execution has which of the following major tasks
i. Developing and prioritizing test cases, creating test data, writing test procedures and optionally preparing the test harnesses and writing automated test scripts.
ii. Creating the test suite from the test cases for efficient test execution.
iii. Verifying that the test environment has been set up correctly.
iv. Determining the exit criteria.
a) i,ii,iii are true and iv is false
b) i,,iv are true and ii is false
c) i,ii are true and iii,iv are false
d) ii,iii,iv are true and i is false

3.A Test Plan Outline contains which of the following :
-
i. Test Items
ii. Test Scripts
iii. Test Deliverables
iv. Responsibilities
a) i,ii,iii are true and iv is false
b) i,iii,iv are true and ii is false
c) ii,iii are true and i and iv are false
d) i,ii are false and iii , iv are true

4. One of the fields on a form contains a text box which accepts numeric values in the range of 18 to 25. Indentify the invalid Equivalance class
a) 17
b) 19
c) 24
d) 21

5. In a Examination a candidate has to score minimum of 24 marks inorder to clear the exam. The maximum that he can score is 40 marks. Identify the Valid Equivalance values if the student clears the exam.
a) 22,23,26
b) 21,39,40
c) 29,30,31
d) 0,15,22

6. Which of the following statements regarding static testing is false:

a) static testing requires the running of tests through the code
b) static testing includes desk checking
c) static testing includes techniques such as reviews and inspections
d) static testing can give measurements such as cyclomatic complexity

7. Verification involves which of the following :
-
i. Helps to check the Quality of the built product
ii. Helps to check that we have built the right product.
iii. Helps in developing the product
iv. Monitoring tool wastage and obsoleteness.
a) Options i,ii,iii,iv are true.
b) i is true and ii,iii,iv are false
c) i,ii,iii are true and iv is false
d) ii is true and i,iii,iv are false.

8. Component Testing is also called as :
-
i. Unit Testing
ii. Program Testing
iii. Module Testing
iv. System Component Testing .
a) i,ii,iii are true and iv is false
b) i,ii,iii,iv are false
c) i,ii,iv are true and iii is false
d) all of above is true

9. Link Testing is also called as :
a) Component Integration testing
b) Component System Testing
c) Component Sub System Testing
d)Maintenance testing

10. What is the expected result for each of the following test cases?
Rule 1
Rule 2
Rule 3
Rule 4
Conditions
Indian resident?
False
True
True
True
Age between 18 – 55?
Don’t care
False
True
True
Married?
Don’t care
Don’t care
False
True
Actions
Issue Memebership?
False
False
True
True
Offer 10% discount?
False
False
True
False
A.TC1:
Anand is a 32 year old married, residing in Kolkatta.
B.TC3:
Attapattu is a 65 year old married person, residing in Colombo.
a.A – Issue membership, 10% discount, B – Issue membership, offer no discount. B
b.A – Don’t Issue membership, B – Don’t offer discount. C
c.A – Issue membership, no discount, B – Don’t Issue membership.
d. Issue membership, no discount, B- Issue membership with 10% discount.

11. Methodologies adopted while performing Maintenance Testing:
- a) Breadth Test and Depth Test
b) Retesting
c) Confirmation Testing
d) Sanity Testing

12. Which of the following is true about Formal Review or Inspection:
- i. Led by Trained Moderator (not the author).
ii. No Pre Meeting Preparations
iii. Formal Follow up process.
iv. Main Objective is to find defects
a) ii is true and i,iii,iv are false
b) i,iii,iv are true and ii is false
c) i,iii,iv are false and ii is true
d) iii is true and I,ii,iv are false

13. The Phases of formal review process is mentioned below arrange them in the correct order.
i. Planning
ii. Review Meeting
iii. Rework
iv. Individual Preparations
v. Kick Off
vi. Follow Up
a) i,ii,iii,iv,v,vi
b) vi,i,ii,iii,iv,v
c) i,v,iv,ii,iii,vi
d) i,ii,iii,v,iv,vi

14. Consider the following state transition diagram of a two-speed hair dryer, which is operated by pressing its one button. The first press of the button turns it on to Speed 1,second press to Speed 2 and the third press turns it off.
Which of the following series of state transitions below will provide 0-switch coverage?

a.A,C,B
b. B,C,A
c.A,B,C
d. C,B,A

15. White Box Techniques are also called as :
- a) Structural Testing
b) Design Based Testing
c) Error Guessing Technique
d) Experience Based Technique

16. What is an equivalence partition (also known as an equivalence class)?
a)A set of test cases for testing classes of objects
b)An input or output range of values such that only one value in the range becomes a test case
c)An input or output range of values such that each value in the range becomes a test Case
d)An input or output range of values such that every tenth value in the range becomes a test case.

17. The Test Cases Derived from use cases
a)Are most useful in uncovering defects in the process flows during real world use of the system
b)Are most useful in uncovering defects in the process flows during the testing use of the system
c)Are most useful in covering the defects in the process flows during real world use of the system d)Are most useful in covering the defects at the Integration Level

18. Exhaustive Testing is
a) Is impractical but possible
b) Is practically possible
c) Is impractical and impossible
d) Is always possible

19. Which of the following is not a part of the Test Implementation and Execution Phase
a) Creating test suites from the test cases
b) Executing test cases either manually or by using test execution tools
c) Comparing actual results
d) Designing the Tests

20. Which of the following techniques is NOT a White box technique?
a) Statement Testing and coverage
b) Decision Testing and coverage
c) Condition Coverage
d) Boundary value analysis

21.A Project risk includes which of the following :
a) Organizational Factors
b) Poor Software characteristics
c) Error Prone software delivered.
d) Software that does not perform its intended functions

22. In a risk-based approach the risks identified may be used to :
i. Determine the test technique to be employed
ii. Determine the extent of testing to be carried out
iii. Prioritize testing in an attempt to find critical defects as early as possible.
iv. Determine the cost of the project
a) ii is True; i, iii, iv & v are False
b) i,ii,iii are true and iv is false
c) ii & iii are True; i, iv are False
d) ii, iii & iv are True; i is false

23. Which of the following is the task of a Tester?
i. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the project.
ii. Prepare and acquire Test Data
iii. Implement Tests on all test levels, execute and log the tests.
iv. Create the Test Specifications
a) i, ii, iii is true and iv is false
b) ii,iii,iv is true and i is false
c) i is true and ii,iii,iv are false
d) iii and iv is correct and i and ii are incorrect

24. The Planning phase of a formal review includes the following :-
a) Explaining the objectives
b) Selecting the personnel, allocating roles.
c) Follow up
d) Individual Meeting preparations

25.A Person who documents all the issues, problems and open points that were identified during a formal review.
a) Moderator.
b) Scribe
c)Author
d) Manager

26. Who are the persons involved in a Formal Review :
- i. Manager
ii. Moderator
iii. Scribe / Recorder
iv.Assistant Manager
a) i,ii,iii,iv are true
b) i,ii,iii are true and iv is false.
c) ii,iii,iv are true and i is false.
d) i,iv are true and ii, iii are false.

27. Which of the following is a Key Characteristics of Walk Through
a) Scenario , Dry Run , Peer Group
b) Pre Meeting Preparations
c) Formal Follow Up Process
d) Includes Metrics

28. What can static analysis NOT find?
a) the use of a variable before it has been defined
b) unreachable (“dead”) code
c) memory leaks
d) array bound violations

29. Incidents would not be raised against:
a) requirements
b) documentation
c) test cases
d) improvements suggested by users

30.A Type of functional Testing, which investigates the functions relating to detection of threats, such as virus from malicious outsiders.
a) Security Testing
b) Recovery Testing
c) Performance Testing
d) Functionality Testing

31. Which of the following is not a major task of Exit criteria?
a) Checking test logs against the exit criteria specified in test planning.
b) Logging the outcome of test execution.
c)Assessing if more tests are needed.
d) Writing a test summary report for stakeholders.

32. Testing where in we subject the target of the test , to varying workloads to measure and evaluate the performance behaviors and ability of the target and of the test to continue to function properly under these different workloads.
a) Load Testing
b) Integration Testing
c) System Testing
d) Usability Testing

33. Testing activity which is performed to expose defects in the interfaces and in the interaction between integrated components is :
- a) System Level Testing
b) Integration Level Testing
c) Unit Level Testing
d) Component Testing

34. Static analysis is best described as:
a) The analysis of batch programs. b) The reviewing of test plans. c) The analysis of program code. d) The use of black box testing.

35. One of the fields on a form contains a text box which accepts alpha numeric values.
Identify the Valid Equivalence class
a) BOOK
b) Book
c) Boo01k
d) book

36. Reviewing the test Basis is a part of which phase
a) Test Analysis and Design
b) Test Implementation and execution
c) Test Closure Activities
d) Evaluating exit criteria and reporting

37. Reporting Discrepancies as incidents is a part of which phase :
- a) Test Analysis and Design
b) Test Implementation and execution
c) Test Closure Activities
d) Evaluating exit criteria and reporting

38. Which of the following items would not come under Configuration Management?
a) operating systems
b) test documentation
c) live data
d) user requirement document

39. Handover of Testware is a part of which Phase
a) Test Analysis and Design
b) Test Planning and control
c) Test Closure Activities
d) Evaluating exit criteria and reporting

40. The Switch is switched off once the temperature falls below 18 and then it is turned on when the temperature is more than 21. When the temperature is more than 21. Identify
the Equivalence values which belong to the same class.

a) 12,16,22
b) 24,27,17
c) 22,23,24
d) 14,15,19

Answers:
1 b
11 a
21 a
31 b
2 a
12 b
22 b
32 a
3 b
13 c
23 b
33 b 4 a
14 c
24 b
34 c 5 c
15 a
25 b
35 c 6 a
16 b
26 b
36 a 7 b
17 a
27 a
37 b 8 a
18 a
28 c
38 c 9 a
19 d
29 d
39 c 10 c
20 d
30 a
40 c






No comments:

Post a Comment